A unit can have its machinery on site and its loan sanctioned, and still not start because one approval was applied for too late. We map every licence your unit needs, put them in the right order and track them through Uttar Pradesh's Nivesh Mitra single window.

Approvals we handle

Fire NOC

Provisional NOC at the building-plan stage, final NOC before occupation, and timely renewals.

Read more

What the approvals roadmap covers

  • Applicability check: which registrations, licences and consents apply to your product, process, scale and location.
  • Sequencing: pre-establishment approvals (land use, building plan, consent to establish, provisional fire NOC, factory plan approval) before construction; pre-operation approvals before trial production.
  • Document pack: site and building plans, process flow, machinery list, CA and engineer certificates in the formats departments expect.
  • Filing and follow-up: Common Application Form on Nivesh Mitra, query responses and tracking against notified timelines.
  • After commissioning: renewals, returns and a compliance calendar so licences do not lapse.

Notified timelines on Nivesh Mitra (selected approvals)

Uttar Pradesh notifies service-delivery timelines for approvals filed through Nivesh Mitra. Departments may raise only one query, within seven days. Selected timelines from the official checklist:

ApprovalDepartmentNotified timeline
Consent to Establish / Consent to OperateUP Pollution Control Board120 days
Fire NOC (provisional / completion / renewal)Fire Services15 days
Factory plan approval; factory registration / licenceLabour (Factories)30 days each
Shops & Establishments registrationLabour1 day
New power connectionUPPCL / discoms30 days

Timelines run from a complete application. In practice the time taken is driven by how complete and consistent the file is, which is where most of our effort goes. FSSAI licensing is handled separately on the FSSAI portal.

Source: Nivesh Mitra approvals checklist